AI data-center demand could outpace power-plant investment: uncertainty and 'cannibalization' of revenues mean private developers may underbuild generation, leaving wholesale electricity prices higher and consumers bearing the cost.
Citation observations
Cumulative provider counts captured on specific dates; providers are never combined.
No provider observation is available for this paper.
Missing data, not a zero citation count.
The twenty-first century's transformative technology, artificial intelligence, is increasingly constrained by the twentieth century's transformative technology, the electricity grid. Rapid growth in electricity demand from data centers is leading to higher electricity prices, without a compensating supply-side response. We develop a framework linking data-center load growth, available generation capacity, and market-clearing prices to understand this phenomenon. We first analyze a deterministic model to show how differing estimates of demand and supply growth rates affect prices. We then model the expansion of new data centers and their associated electricity demand, together with build-outs of new electricity supply, as stochastic processes,resulting in probabilistic distributions of supply, demand, and prices rather than a single forecast. Finally, we formulate generation expansion as a stochastic control problem in which a revenue-maximizing investor dynamically chooses the intensity of supply-side investments. The analysis highlights a central challenge of the data-center build-out: even when rapid demand growth increases the need for new generation, the uncertainties related to load forecasts, development execution risks, and value cannibalization from overbuilding capacity may weaken incentives to invest at the pace required to keep electricity prices stable.
Summary
Main Finding
Rapid, lumpy growth in AI data-center electricity demand can raise wholesale electricity prices substantially, but the same price signals that justify new generation also reduce the future revenues of entrants (a “revenue cannibalization” effect). Under realistic ERCOT/Texas-calibrated parameters, stochastic uncertainty in data-center arrivals and long, lumpy build times for generation weaken private incentives to build capacity at the pace needed to stabilize prices — so prices may rise and remain elevated unless policy or contracting corrects coordination and timing failures.
Key Points
- Conceptual framing: the paper links reference demand from two groups (traditional users and hyperscaler data centers), available accredited generation capacity, and a market-clearing price determined by D(I,X,P)=S.
- Demand heterogeneity: hyperscalers are modeled as much less price-sensitive than traditional users (choke prices A1=$70/MWh, A2=$150/MWh; normalized at reference price P0=$30/MWh).
- Deterministic benchmark:
- If supply is fixed, data-center growth can substantially raise prices (example: price could double from $30 to ~$60/MWh over 10 years under calibrated assumptions).
- Linear supply growth at different rates can either offset price pressure or, if fast, cause prices to fall (illustrating cannibalization).
- Stochastic model:
- Data-center build-outs modeled as a compound Poisson process: arrivals N^µ_t with lognormal jump sizes Yk (calibrated to Texas campus capacities, mean 0.225 GW, sd 1.54 GW) to capture rare very large facilities.
- Supply additions modeled by independent Poisson processes by technology j (natural gas, coal, solar, wind, large-scale nuclear, SMRs) with technology-specific intensities λ_j and per-arrival capacity δ_j (Table 1).
- Calibration: reference parameters chosen to match ERCOT/Texas (P0=$30/MWh, I0=55 GW, X0=8 GW; targeted data-center growth c_X=6 GW/yr → µ≈26/yr).
- Monte Carlo results (N=1000, horizon 2025–2031):
- Terminal price mean ≈ $33.43/MWh, SD ≈ $5.87/MWh; distributions show non-negligible probability of higher prices (and also of prices falling below baseline if supply additions cluster).
- Representative sample paths illustrate wide dispersion in supply, demand, and prices due to lumpy arrivals.
- Investment incentives and cannibalization:
- The authors formulate generation expansion as a stochastic control problem: a revenue-maximizing investor chooses investment intensity under uncertainty in demand growth and build completions.
- Successful investment reduces future market prices and therefore erodes its own (and incumbents’) expected revenues. When this cannibalization and uncertainty dominate, optimal private investment can be insufficient or delayed even when aggregate demand growth argues for faster build-out.
- Policy-relevant observation: even large price spikes do not guarantee timely, sufficient entry because of long lead times, permitting and interconnection frictions, skewed project sizes, and value cannibalization.
Data & Methods
- Analytical setup:
- Market clearing: total accredited supply S_t equals price-responsive demand D(I_t,X_t,P_t), with D split into D1=I_t F1(P) and D2=X_t F2(P). F1, F2 chosen decreasing, normalized to 1 at P0.
- Deterministic scenarios: closed-form/ numerical solutions for price paths under fixed or linearly growing supply and demand.
- Stochastic modeling:
- Data centers: compound Poisson process X_t = X0 + Σ_{k=1}^{N^µ_t} Y_k; Y_k ~ lognormal (MLE fit to Texas capacities excluding outlier Project Matador), µ calibrated so E[annual growth]=6 GW/yr.
- Supply: S_t = S0 + Σ_j δ_j N^{λ_j}_t with independent Poisson processes per technology j; technology parameters λ_j, δ_j calibrated from 2015–2025 capacity-addition data (SMR parameters assumed due to lack of history). Example baseline table: natural gas (λ=10/yr, δ=250 MW), solar (λ=40/yr, δ=50 MW), etc.
- Market-clearing price solved implicitly from D(I_t,X_t,P_t)=S_t at each simulated date (long-run monthly average price interpretation).
- Simulations:
- Monte Carlo (1000 runs) over T=6 years (2025–31), producing distributions of S_t, X_t, and P_t. Summary statistics reported (mean, SD, distribution plots).
- Stochastic control:
- Formulate generation expansion as a controlled-intensity jump process where an investor selects investment intensity to maximize discounted expected revenue accounting for stochastic demand arrivals and price impact from capacity additions (i.e., cannibalization). The paper analyzes qualitative trade-offs and comparative statics across technologies differing in cost, size, and build time.
Implications for AI Economics
- Market signals alone may not deliver socially optimal capacity expansion:
- Price spikes can be necessary but not sufficient to spur timely entry because project lumpy sizes, long lead times, and cannibalization reduce expected returns to investors.
- Need for coordination mechanisms:
- Policy interventions (streamlined permitting/interconnection, transmission build-out, targeted subsidies, capacity markets, long-term contracts, offtake agreements) can reduce uncertainty, internalize externalities, and align private incentives with social needs.
- Technology-choice and timing matter:
- Faster-to-deploy resources (solar, gas) can relieve near-term scarcity but may be politically constrained and intermittent, whereas firm technologies (gas, nuclear/SMR) have long lead times and higher up-front costs; optimal mixes depend on expected demand growth and risk tolerance.
- Data-center siting and contract design:
- Hyperscalers’ lower price responsiveness implies they impose high reliability/value requirements; regulators and grid planners may want pricing or locational charges that reflect true network costs, or encourage data centers to sign firm long-term capacity contracts to signal demand and finance supply.
- Implications for AI deployment costs:
- If electricity prices rise materially and persist, the marginal cost of operating large AI models increases, potentially affecting deployment decisions, geographic location of compute, and the social cost of AI scaling.
- Research and policy gaps:
- The model abstracts from transmission constraints, retirements, short-run intermittency, distributional effects, and interactions between real-time and long-run prices — all important for designing practical interventions.
- Practical takeaway: managing AI-driven electricity demand growth requires active coordination (planning, contracting, regulatory reform) rather than reliance on decentralised price signals alone; otherwise private underinvestment and lumpy supply arrivals can leave grids strained and consumers exposed to higher bills.
Assessment
Claims (10)
| Claim | Direction | Outcome | Confidence & Evidence | Details |
|---|---|---|---|---|
| U.S. electricity demand from data centers increased from 76 TWh in 2018 to more than 200 TWh in 2025, while data centers' share of total U.S. electricity demand rose from 1.9% to 4.8%. Adoption Rate | positive | Data-center electricity demand and its share of total U.S. electricity demand |
Reading fidelity
high
Study strength
medium
|
76 TWh to more than 200 TWh; 1.9% to 4.8%
|
| ERCOT forecast 33 GW of new demand from data centers and cryptocurrency mining by 2031, equivalent to a 36% increase relative to its all-time system peak of 91 GW. Adoption Rate | positive | Projected additional electricity demand |
Reading fidelity
high
Study strength
medium
|
33 GW; 36% increase relative to 91 GW
|
| In the paper's deterministic model with no supply growth and linear data-center reference-demand growth of 6 GW per year, electricity prices would double from $30/MWh to $60/MWh over 10 years. Consumer Welfare | positive | Wholesale electricity price under fixed supply |
Reading fidelity
high
Study strength
medium
|
$30/MWh to $60/MWh over 10 years
|
| In the deterministic model, when supply grows slowly, demand growth dominates and prices rise; sufficiently rapid supply growth instead causes prices to fall because of revenue cannibalization. Consumer Welfare | mixed | Average annual wholesale electricity price |
Reading fidelity
high
Study strength
medium
|
not reported
|
| The model assumes hyperscaler demand is less price-sensitive than traditional electricity demand, so higher prices reduce hyperscaler demand less than traditional demand. Task Allocation | positive | Relative price sensitivity of hyperscaler versus traditional electricity demand |
Reading fidelity
high
Study strength
low
|
A1 = $70/MWh; A2 = $150/MWh
|
| The stochastic data-center demand model is calibrated so that expected data-center reference-demand growth is 6 GW per year, using an arrival intensity of approximately 26 data centers per year and a mean demand increment of 0.225 GW per arrival. Adoption Rate | positive | Expected annual data-center electricity-demand additions |
Reading fidelity
high
Study strength
medium
|
6 GW/year; approximately 26 arrivals/year; 0.225 GW mean increment
|
| The fitted lognormal distribution for Texas data-center capacity additions has a mean of 0.225 GW and a standard deviation of 1.54 GW, reflecting a heavy right tail. Adoption Rate | positive | Distribution of data-center capacity additions |
Reading fidelity
high
Study strength
medium
|
mean 0.225 GW; standard deviation 1.54 GW
|
| Across 1,000 Monte Carlo simulations of the Texas electricity market over 2025–2031, the mean terminal wholesale electricity price in 2031 was $33.43/MWh with a standard deviation of $5.87/MWh. Consumer Welfare | positive | Terminal wholesale electricity price in 2031 |
Reading fidelity
high
Study strength
medium
|
n=1000
mean $33.43/MWh; standard deviation $5.87/MWh
|
| The stochastic model permits terminal electricity prices to fall below the baseline reference price of $30/MWh. Consumer Welfare | negative | Wholesale electricity prices relative to the $30/MWh baseline |
Reading fidelity
high
Study strength
medium
|
n=1000
|
| PJM's independent market monitor attributed 40% of the costs in the December 2025 capacity auction to data centers expected to come online in 2027 and 2028. Consumer Welfare | positive | Share of capacity-auction costs attributed to future data-center load |
Reading fidelity
high
Study strength
medium
|
40%
|